The Job Construction Schedule report generates the list of tasks within a specific Construction Schedule in the basic or worksheet format.
- Open the library with reports.
 - Select Job Construction Schedule.
 - Define criteria for generating the report, as follows:
 
Criteria
| Schedule | Select the schedule which the report is generated for. | 
| Format | Select the format for report generation. | 

4. When complete, click Apply. The report in the basic format is generated, as follows:

The report shows the following information:
Job Details
| 
 JOB DETAILS  | |
| Job | Job number including the Office’s number as prefix. | 
| Site | Site where the construction work is performed. | 
| House | House plan used for the Job construction. | 
| Floor Area | Floor area of the House. | 
| Start | Start date of the Job. | 
| Client | Name of the Client who the Job attributes to. | 
| Address | Address of the Client. | 
| Contact | Contact email address of the Client. | 
| Phone | Phone number of the Client. | 
| Fax | Fax number of the Client. | 
| 
 TASKS  | |
| Task / Sub-task | Description of the Critical Path stage or description of the sub-task. | 
| Start on Day N | Day which the Critical Path stage starts on. | 
| End on Day N | Day which the Critical Path stage ends on. | 
| Supplier / Resource | Supplier or Resource that performs the sub-task. | 
| Order Date | Date when the sub-task was ordered. | 
| Start | Start date of the sub-task. | 
| Finish | Finish date of the sub-task. | 
| Done | Completion status of the Critical Path stage or of the sub-task. | 
The report in the worksheet format is generated, as follows:

The set of information in this report format is identical to the basic format.
														
							